PG-05 · O2 A safe and prepared community · MG-05
Licensing simplification
Owner D. Nkemelu. 26/02/2026 to 21/02/2027. Baseline 1. Depends on PG-06.
GREENACTIVE
Budget burn
63%
$300,000 of $480,000
Schedule elapsed
56%
variance +7 points
Milestones
1/3
MS-0502 late
Finding
none
tracking agent
Budget burn
Cumulative planned against actual by period
No budget lines.
Benefits and indicators
- Days to issue · target 7 days · now 6 (2026-Q2, MG-05 live)
Milestones
Baseline and current due dates; completion needs evidence
| Ref | Milestone | Owner | Baseline due | Due | Completed | Status | |
|---|---|---|---|---|---|---|---|
| MS-0501 | Standard conditions published | D. Nkemelu | 26/06/2026 | 26/06/2026 | 27/06/2026 | DONE | |
| MS-0502 | Automatic mutual recognition | D. Nkemelu | 30/08/2026 | 30/08/2026 | LATE | ||
| MS-0503 | Renewals verified from monitoring data | D. Nkemelu | 29/10/2026 | 29/10/2026 | PLANNED |
Request a re-baseline
The executive decides (GL-PG-01)
Program log
- No events yet.