PG-05 · O2 A safe and prepared community · MG-05

Licensing simplification

Owner D. Nkemelu. 26/02/2026 to 21/02/2027. Baseline 1. Depends on PG-06.

GREENACTIVE

Budget burn

63%

$300,000 of $480,000

Schedule elapsed

56%

variance +7 points

Milestones

1/3

MS-0502 late

Finding

none

tracking agent

Budget burn

Cumulative planned against actual by period

No budget lines.

Benefits and indicators

  • Days to issue · target 7 days · now 6 (2026-Q2, MG-05 live)

Milestones

Baseline and current due dates; completion needs evidence

RefMilestoneOwnerBaseline dueDueCompletedStatus
MS-0501Standard conditions publishedD. Nkemelu26/06/202626/06/202627/06/2026DONE
MS-0502Automatic mutual recognitionD. Nkemelu30/08/202630/08/2026LATE
MS-0503Renewals verified from monitoring dataD. Nkemelu29/10/202629/10/2026PLANNED

Request a re-baseline

The executive decides (GL-PG-01)

Program log

  • No events yet.